Assessment Year | 2005 |
---|---|
Principal Product | Construction Nails |
NAICS | 332613: Spring Manufacturing |
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $50 M to 100M |
# of Employees | 80 |
Plant Area |
80,000
ft2
|
Annual Production | 48,000
ton
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $238,778 | 2,920,779 |
kWh
|
$0.082 |
Electricity Demand | $98,608 | 7,148 |
kW-mo/yr
|
$13.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $286,721 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $83,605 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4238: Do not use compressed air for personal cooling | $41,074 | $6,300 |
$30,711
375,447
kWh
|
$10,363
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $16,917 | - |
$16,917
206,812
kWh
|
- | - | |
03 | 2.7135: Install occupancy sensors | $14,251 | $3,500 |
$14,251
174,221
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,614 | $26,000 |
$7,978
97,528
kWh
|
$2,636
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $749 | $80 |
$560
6,848
kWh
|
$189
-
kW-mo/yr
|
- | |
06 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $194,956 | $92,000 |
$(-1,220.0)
(-14,920)
kWh
|
$(-6,177.0)
-
kW-mo/yr
|
$202,353
-
lb
|
|
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $8,160 | $18,500 | - | - |
$8,160
-
lb
|
|
TOTAL RECOMMENDED | $286,721 | $146,380 |
$69,197
845,936
kWh
|
$7,011
-
kW-mo/yr
|
$210,513
-
lb
|
||
TOTAL IMPLEMENTED | $83,605 | $35,880 |
$70,417
860,856
kWh
|
$13,188
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs