Assessment Year | 2004 |
---|---|
Principal Product | Bricks |
NAICS | 327120: Clay Building Material and Refractories Manufacturing |
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
150,000
ft2
|
Annual Production | 80,000,000
pieces
|
Production Hrs. Annual | 7,224
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $114,480 | 1,594,732 |
kWh
|
$0.072 |
Electricity Demand | $72,118 | 7,425 |
kW-mo/yr
|
$9.71 |
Natural Gas | $488,108 | 89,289 |
MMBtu
|
$5.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $344,943 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $127,079 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $217,864 | $75,000 | - | - |
$217,864
-
MMBtu
|
- | |
02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $80,766 | $255,442 |
$107,765
1,502,997
kWh
|
$25,518
-
kW-mo/yr
|
$(-52,517.0)
-
MMBtu
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $34,754 | $39,050 |
$28,375
395,752
kWh
|
$6,379
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,248 | $14,785 |
$5,918
82,541
kWh
|
$1,330
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,257 | $350 |
$1,393
20,825
kWh
|
$864
-
kW-mo/yr
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $663 | - |
$663
9,243
kWh
|
- | - | - | |
07 | 2.8123: Pay utility bills on time | $1,391 | - | - | - | - | $1,391 | |
TOTAL RECOMMENDED | $344,943 | $384,627 |
$144,114
2,011,358
kWh
|
$34,091
-
kW-mo/yr
|
$165,347
-
MMBtu
|
$1,391 | ||
TOTAL IMPLEMENTED | $127,079 | $309,627 |
$144,114
2,011,358
kWh
|
$34,091
-
kW-mo/yr
|
$(-52,517.0)
-
MMBtu
|
$1,391 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs