ITAC Assessment: SD0321
ITAC logo
ITAC Assessment: SD0321
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Seals
NAICS 339991: Gasket, Packing, and Sealing Device Manufacturing
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $50
M
to 100
M
# of Employees 120
Plant Area 70,000
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $172,680 2,068,411
kWh
Electricity Demand $58,992 5,253
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $99,263 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,234

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $74,855 $44,000 $63,063
735,000
kWh
$11,792
-
kW-mo/yr
-
02 2.6218: Turn off equipment when not in use $10,234 - $10,234
119,280
kWh
- -
03 2.4239: Eliminate or reduce compressed air usage $4,011 $2,300 $541
6,303
kWh
$3,470
-
kW-mo/yr
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,845 - $2,250
26,229
kWh
$595
-
kW-mo/yr
-
05 2.2614: Use cooling tower or economizer to replace chiller cooling $2,842 $5,400 $2,763
32,198
kWh
$79
-
kW-mo/yr
-
06 2.7134: Use photocell controls $1,476 $582 $721
8,400
kWh
$755
-
kW-mo/yr
-
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,000 $5,000 - - $3,000
-
lb
TOTAL RECOMMENDED $99,263 $57,282 $79,572
927,410
kWh
$16,691
-
kW-mo/yr
$3,000
-
lb
TOTAL IMPLEMENTED $10,234 - $10,234
119,280
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs