Assessment Year | 2003 |
---|---|
Principal Product | Seals |
NAICS | 339991: Gasket, Packing, and Sealing Device Manufacturing |
SIC | 3053: Gaskets, Packing, and Sealing Devices |
Sales Range | $50 M to 100M |
# of Employees | 120 |
Plant Area |
70,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $172,680 | 2,068,411 |
kWh
|
$0.083 |
Electricity Demand | $58,992 | 5,253 |
kW-mo/yr
|
$11.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $99,263 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,234 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $74,855 | $44,000 |
$63,063
735,000
kWh
|
$11,792
-
kW-mo/yr
|
- | |
02 | 2.6218: Turn off equipment when not in use | $10,234 | - |
$10,234
119,280
kWh
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $4,011 | $2,300 |
$541
6,303
kWh
|
$3,470
-
kW-mo/yr
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,845 | - |
$2,250
26,229
kWh
|
$595
-
kW-mo/yr
|
- | |
05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,842 | $5,400 |
$2,763
32,198
kWh
|
$79
-
kW-mo/yr
|
- | |
06 | 2.7134: Use photocell controls | $1,476 | $582 |
$721
8,400
kWh
|
$755
-
kW-mo/yr
|
- | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,000 | $5,000 | - | - |
$3,000
-
lb
|
|
TOTAL RECOMMENDED | $99,263 | $57,282 |
$79,572
927,410
kWh
|
$16,691
-
kW-mo/yr
|
$3,000
-
lb
|
||
TOTAL IMPLEMENTED | $10,234 | - |
$10,234
119,280
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs