ITAC Assessment: SD0319
ITAC logo
ITAC Assessment: SD0319
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product plastic and rubber products
NAICS 326291: Rubber Product Manufacturing for Mechanical Use
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $50
M
to 100
M
# of Employees 600
Plant Area 290,000
ft2
Annual Production 500,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,397,224 12,950,491
kWh
Electricity Demand $412,086 34,564
kW-mo/yr
Natural Gas $509,451 71,836
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $639,009 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $263,736

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $81,424 $31,100 $67,919
629,465
kWh
$13,505
-
kW-mo/yr
- - - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $70,391 $78,000 $48,264
447,300
kWh
$36,559
-
kW-mo/yr
$(-14,432.0)
-
MMBtu
- - - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $31,150 $14,100 $28,051
259,974
kWh
$3,099
-
kW-mo/yr
- - - - -
04 2.6218: Turn off equipment when not in use $29,977 $1,515 $14,243
132,000
kWh
$15,734
-
kW-mo/yr
- - - - -
05 2.2113: Repair or replace steam traps $22,467 $9,950 - - $22,467
-
MMBtu
- - - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $22,675 $10,950 $18,575
172,154
kWh
$4,100
-
kW-mo/yr
- - - - -
07 2.4321: Upgrade obsolete equipment $14,674 $160 $12,016
111,360
kWh
$2,658
-
kW-mo/yr
- - - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $13,816 - $11,313
104,850
kWh
$2,503
-
kW-mo/yr
- - - - -
09 2.2135: Repair and eliminate steam leaks $7,163 $6,600 - - $7,163
-
MMBtu
- - - -
10 2.6218: Turn off equipment when not in use $11,780 $1,550 $6,440
59,680
kWh
$5,340
-
kW-mo/yr
- - - - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,312 $240 $8,446
78,286
kWh
$1,866
-
kW-mo/yr
- - - - -
12 2.7145: Install skylights $8,457 $23,000 $4,489
41,602
kWh
$3,968
-
kW-mo/yr
- - - - -
13 2.6218: Turn off equipment when not in use $3,005 $1,500 $1,932
17,904
kWh
$1,073
-
kW-mo/yr
- - - - -
14 2.7135: Install occupancy sensors $2,734 $750 $898
8,320
kWh
$1,836
-
kW-mo/yr
- - - - -
15 2.2153: Close off unneeded steam lines $2,248 $1,350 - - $2,248
-
MMBtu
- - - -
16 3.1192: Reduce scrap production $222,070 $9,000 - - - - $10,070
-
lb
$212,000 -
17 3.1192: Reduce scrap production $52,500 $15,360 - - - - - - $52,500
18 3.1192: Reduce scrap production $30,000 $1,400 - - - - - $30,000 -
19 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,166 - - - - $2,166
-
lb
- - -
TOTAL RECOMMENDED $639,009 $206,525 $222,586
2,062,895
kWh
$92,241
-
kW-mo/yr
$17,446
-
MMBtu
$2,166
-
lb
$10,070
-
lb
$242,000 $52,500
TOTAL IMPLEMENTED $263,736 $23,350 $8,372
77,584
kWh
$6,413
-
kW-mo/yr
$24,715
-
MMBtu
$2,166
-
lb
$10,070
-
lb
$212,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs