Assessment Year | 2003 |
---|---|
Principal Product | Boat |
NAICS | 336612: Boat Building |
SIC | 3732: Boat Building and Repairing |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
95,000
ft2
|
Annual Production | 3
pieces
|
Production Hrs. Annual | 2,338
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,876 | 653,400 |
kWh
|
$0.095 |
Electricity Demand | $23,916 | 2,082 |
kW-mo/yr
|
$11.49 |
Natural Gas | $1,088 | 158 |
MMBtu
|
$6.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,599 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $781 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7134: Use photocell controls | $16,275 | $11,000 |
$8,646
91,300
kWh
|
$7,629
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,368 | - |
$1,473
15,519
kWh
|
$895
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,675 | $400 |
$1,032
10,899
kWh
|
$643
-
kW-mo/yr
|
- | |
04 | 2.6218: Turn off equipment when not in use | $781 | - |
$781
8,250
kWh
|
- | - | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,500 | $10,000 | - | - | $7,500 | |
TOTAL RECOMMENDED | $28,599 | $21,400 |
$11,932
125,968
kWh
|
$9,167
-
kW-mo/yr
|
$7,500 | ||
TOTAL IMPLEMENTED | $781 | - |
$781
8,250
kWh
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs