Assessment Year | 2002 |
---|---|
Principal Product | rebar fabrication |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
270,000
ft2
|
Annual Production | 60,000
ton
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $98,442 | 809,706 |
kWh
|
$0.12 |
Electricity Demand | $20,813 | 2,518 |
kW-mo/yr
|
$8.27 |
Electricity Fees | $720 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,386 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,468 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,205 | $23,000 |
$2,270
45,812
kWh
|
$935
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,006 | $240 |
$4,998
41,105
kWh
|
$8
-
kW-mo/yr
|
- | |
03 | 2.7226: Use computer programs to optimize hvac performance | $3,708 | $1,000 |
$3,708
30,496
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,521 | $6,822 |
$1,942
15,971
kWh
|
$579
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,468 | - |
$2,129
17,510
kWh
|
$339
-
kW-mo/yr
|
- | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,478 | $5,000 | - | - |
$2,478
-
lb
|
|
TOTAL RECOMMENDED | $19,386 | $36,062 |
$15,047
150,894
kWh
|
$1,861
-
kW-mo/yr
|
$2,478
-
lb
|
||
TOTAL IMPLEMENTED | $2,468 | - |
$2,129
17,510
kWh
|
$339
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs