ITAC Assessment: SD0306
ITAC logo
ITAC Assessment: SD0306
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product rebar fabrication
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 270,000
ft2
Annual Production 60,000
ton
Production Hrs. Annual 5,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $98,442 809,706
kWh
Electricity Demand $20,813 2,518
kW-mo/yr
Electricity Fees $720 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,386 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,468

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,205 $23,000 $2,270
45,812
kWh
$935
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,006 $240 $4,998
41,105
kWh
$8
-
kW-mo/yr
-
03 2.7226: Use computer programs to optimize hvac performance $3,708 $1,000 $3,708
30,496
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,521 $6,822 $1,942
15,971
kWh
$579
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,468 - $2,129
17,510
kWh
$339
-
kW-mo/yr
-
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,478 $5,000 - - $2,478
-
lb
TOTAL RECOMMENDED $19,386 $36,062 $15,047
150,894
kWh
$1,861
-
kW-mo/yr
$2,478
-
lb
TOTAL IMPLEMENTED $2,468 - $2,129
17,510
kWh
$339
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs