Assessment Year | 2002 |
---|---|
Principal Product | Valves |
NAICS |
n/a
|
SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
Sales Range | n/a |
# of Employees | 250 |
Plant Area |
95,028
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $248,057 | 2,264,529 |
kWh
|
$0.11 |
Electricity Demand | $98,250 | 7,761 |
kW-mo/yr
|
$12.66 |
Electricity Fees | $3,478 | - |
|
- |
Natural Gas | $15,704 | 2,204 |
MMBtu
|
$7.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,382 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $427 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,323 | $34,000 |
$11,633
106,224
kWh
|
$2,690
-
kW-mo/yr
|
- | - | - | |
02 | 2.7145: Install skylights | $6,262 | $2,000 |
$3,253
29,709
kWh
|
$3,009
-
kW-mo/yr
|
- | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,968 | $12,000 |
$3,231
29,520
kWh
|
$3,737
-
kW-mo/yr
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,228 | - |
$1,681
15,353
kWh
|
$1,547
-
kW-mo/yr
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $964 | $800 |
$964
8,800
kWh
|
- | - | - | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,000 | $10,000 | - | - |
$5,000
-
lb
|
- | - | |
07 | 3.3125: Use distillation, evaporation to remove contaminants | $5,210 | $6,000 | - | - | - |
$5,210
-
lb
|
- | |
08 | 2.8123: Pay utility bills on time | $427 | - | - | - | - | - | $427 | |
TOTAL RECOMMENDED | $42,382 | $64,800 |
$20,762
189,606
kWh
|
$10,983
-
kW-mo/yr
|
$5,000
-
lb
|
$5,210
-
lb
|
$427 | ||
TOTAL IMPLEMENTED | $427 | - | - | - | - | - | $427 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs