ITAC Assessment: SD0302
ITAC logo
ITAC Assessment: SD0302
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Valves
NAICS
n/a
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range n/a
# of Employees 250
Plant Area 95,028
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $248,057 2,264,529
kWh
Electricity Demand $98,250 7,761
kW-mo/yr
Electricity Fees $3,478 -
Natural Gas $15,704 2,204
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,382 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $427

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $14,323 $34,000 $11,633
106,224
kWh
$2,690
-
kW-mo/yr
- - -
02 2.7145: Install skylights $6,262 $2,000 $3,253
29,709
kWh
$3,009
-
kW-mo/yr
- - -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $6,968 $12,000 $3,231
29,520
kWh
$3,737
-
kW-mo/yr
- - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $3,228 - $1,681
15,353
kWh
$1,547
-
kW-mo/yr
- - -
05 2.7135: Install occupancy sensors $964 $800 $964
8,800
kWh
- - - -
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,000 $10,000 - - $5,000
-
lb
- -
07 3.3125: Use distillation, evaporation to remove contaminants $5,210 $6,000 - - - $5,210
-
lb
-
08 2.8123: Pay utility bills on time $427 - - - - - $427
TOTAL RECOMMENDED $42,382 $64,800 $20,762
189,606
kWh
$10,983
-
kW-mo/yr
$5,000
-
lb
$5,210
-
lb
$427
TOTAL IMPLEMENTED $427 - - - - - $427
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs