ITAC Assessment: SD0299
ITAC logo
ITAC Assessment: SD0299
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Wrought iron furniture
NAICS
n/a
SIC 2514: Metal Household Furniture
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 97,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 4,125
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,816 613,800
kWh
Electricity Demand $18,613 2,288
kW-mo/yr
Electricity Fees $1,447 -
Natural Gas $42,546 6,590
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $231,732 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,800

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7145: Install skylights $3,373 $5,200 $2,119
19,260
kWh
$1,254
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,114 $4,526 $2,327
21,155
kWh
$787
-
kW-mo/yr
- - - -
03 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $2,389 - $1,965
17,866
kWh
$424
-
kW-mo/yr
- - - -
04 2.6218: Turn off equipment when not in use $2,238 $400 $2,238
20,344
kWh
- - - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $752 - $532
4,835
kWh
$220
-
kW-mo/yr
- - - -
06 2.7135: Install occupancy sensors $376 $250 $238
2,160
kWh
$138
-
kW-mo/yr
- - - -
07 3.6192: Use a less expensive method of waste removal $4,300 $3,000 - - - $4,300
-
lb
- -
08 3.7134: Wash and reuse rags on-site $3,040 $5,000 - - - $3,040
-
lb
- -
09 3.6193: Install equipment (eg compactor) to reduce disposal costs $7,250 $15,000 - - - $7,250
-
lb
- -
10 3.5217: Reuse / recycle/ sell paper products $1,250 $2,500 - - - $1,250
-
lb
- -
11 3.5311: Recover and reuse waste material $39,000 $12,000 - - $39,000
-
gal
- - -
12 3.1192: Reduce scrap production $8,350 - - - - $8,350
-
lb
- -
13 3.2176: Increase use of automation $51,000 $55,000 - - - - $51,000 -
14 4.211: Consider use / purchase of bulk materials where possible $37,800 - - - - - - $37,800
15 3.2176: Increase use of automation $51,000 $55,000 - - - - $51,000 -
16 3.2176: Increase use of automation $16,500 - - - - - $16,500 -
TOTAL RECOMMENDED $231,732 $157,876 $9,419
85,620
kWh
$2,823
-
kW-mo/yr
$39,000
-
gal
$24,190
-
lb
$118,500 $37,800
TOTAL IMPLEMENTED $12,800 $20,500 - - - $12,800
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs