Assessment Year | 2002 |
---|---|
Principal Product | pizza |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | n/a |
# of Employees | 300 |
Plant Area |
70,000
ft2
|
Annual Production | 171,360,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $725,011 | 7,133,045 |
kWh
|
$0.10 |
Electricity Demand | $187,466 | 13,766 |
kW-mo/yr
|
$13.62 |
Electricity Fees | $3,588 | - |
|
- |
Natural Gas | $359,466 | 59,240 |
MMBtu
|
$6.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $664,263 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $417,930 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2694: Use highest temperature for chilling or cold storage | $9,645 | $200 |
$9,645
94,955
kWh
|
- | - | - | |
02 | 2.3132: Recharge batteries on during off-peak demand periods | $3,840 | - | - |
$3,840
-
kW-mo/yr
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $26,967 | - |
$26,462
26,462
kWh
|
$505
-
kW-mo/yr
|
- | - | |
04 | 2.7134: Use photocell controls | $1,578 | $1,000 |
$901
8,868
kWh
|
$677
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,373 | $3,000 |
$1,181
11,625
kWh
|
$192
-
kW-mo/yr
|
- | - | |
06 | 2.7145: Install skylights | $543 | $1,200 |
$310
3,052
kWh
|
$233
-
kW-mo/yr
|
- | - | |
07 | 3.5311: Recover and reuse waste material | $198,000 | $15,000 | - | - |
$198,000
-
lb
|
- | |
08 | 4.441: Install automatic packing equipment | $416,352 | $655,000 | - | - | - | $416,352 | |
09 | 4.441: Install automatic packing equipment | $5,965 | $3,500 | - | - | - | $5,965 | |
TOTAL RECOMMENDED | $664,263 | $678,900 |
$38,499
144,962
kWh
|
$5,447
-
kW-mo/yr
|
$198,000
-
lb
|
$422,317 | ||
TOTAL IMPLEMENTED | $417,930 | $656,000 |
$901
8,868
kWh
|
$677
-
kW-mo/yr
|
- | $416,352 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs