Assessment Year | 2002 |
---|---|
Principal Product | sand |
NAICS |
n/a
|
SIC | 1446: Industrial Sand |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
52,272,000
ft2
|
Annual Production | 500,000
ton
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $964,439 | 11,919,186 |
kWh
|
$0.081 |
Electricity Demand | $271,415 | 23,892 |
kW-mo/yr
|
$11.36 |
Electricity Fees | $2,705 | - |
|
- |
Natural Gas | $1,362,409 | 134,098 |
MMBtu
|
$10.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,680 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,172 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $35,696 | $30,000 |
$29,732
367,519
kWh
|
$5,964
-
kW-mo/yr
|
- | |
02 | 2.7145: Install skylights | $3,317 | $5,500 |
$1,715
21,204
kWh
|
$1,602
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,172 | $30,000 |
$18,469
228,291
kWh
|
$3,703
-
kW-mo/yr
|
- | |
04 | 3.6192: Use a less expensive method of waste removal | $3,495 | - | - | - |
$3,495
-
gal
|
|
TOTAL RECOMMENDED | $64,680 | $65,500 |
$49,916
617,014
kWh
|
$11,269
-
kW-mo/yr
|
$3,495
-
gal
|
||
TOTAL IMPLEMENTED | $22,172 | $30,000 |
$18,469
228,291
kWh
|
$3,703
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs