ITAC Assessment: SD0288
ITAC logo
ITAC Assessment: SD0288
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product sand
NAICS
n/a
SIC 1446: Industrial Sand
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 52,272,000
ft2
Annual Production 500,000
ton
Production Hrs. Annual 8,400
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $964,439 11,919,186
kWh
Electricity Demand $271,415 23,892
kW-mo/yr
Electricity Fees $2,705 -
Natural Gas $1,362,409 134,098
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $64,680 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,172

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $35,696 $30,000 $29,732
367,519
kWh
$5,964
-
kW-mo/yr
-
02 2.7145: Install skylights $3,317 $5,500 $1,715
21,204
kWh
$1,602
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $22,172 $30,000 $18,469
228,291
kWh
$3,703
-
kW-mo/yr
-
04 3.6192: Use a less expensive method of waste removal $3,495 - - - $3,495
-
gal
TOTAL RECOMMENDED $64,680 $65,500 $49,916
617,014
kWh
$11,269
-
kW-mo/yr
$3,495
-
gal
TOTAL IMPLEMENTED $22,172 $30,000 $18,469
228,291
kWh
$3,703
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs