| Assessment Year | 2002 |
|---|---|
| Principal Product | Pneumatic,hydraulic and fuel fittings |
| NAICS |
n/a
|
| SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 400 |
| Plant Area |
609,840
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,732
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $890,354 | 6,531,261 |
kWh
|
$0.14 |
| Electricity Demand | $55,946 | 7,146 |
kW-mo/yr
|
$7.83 |
| Electricity Fees | $5,546 | - |
|
- |
| Natural Gas | $39,991 | 5,076 |
MMBtu
|
$7.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $283,081 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $41,211 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,881 | $1,440 |
$5,221
62,981
kWh
|
$1,660
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $51,269 | $35,000 |
$33,485
403,920
kWh
|
$17,784
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $27,450 | $20,000 |
$20,817
251,104
kWh
|
$6,633
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.3137: Use power during off-peak periods | $30,695 | - | - |
$19,184
-
kW-mo/yr
|
$11,511 | - | - | - | |
| 05 | 2.7145: Install skylights | $41,280 | $31,500 | - |
$23,134
-
kW-mo/yr
|
$18,146 | - | - | - | |
| 06 | 2.4322: Use or replace with energy efficient substitutes | $13,283 | $3,000 |
$10,073
170,214
kWh
|
$3,210
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.7135: Install occupancy sensors | $3,635 | $2,800 |
$3,635
43,842
kWh
|
- | - | - | - | - | |
| 08 | 2.6218: Turn off equipment when not in use | $20,169 | $2,500 |
$15,249
186,112
kWh
|
$4,920
-
kW-mo/yr
|
- | - | - | - | |
| 09 | 3.3131: Use evaporation to concentrate material | $6,810 | $3,000 | - | - | - |
$6,810
-
gal
|
- | - | |
| 10 | 3.3131: Use evaporation to concentrate material | $825 | $1,500 | - | - | - | - |
$825
-
lb
|
- | |
| 11 | 4.445: Install equipment to move product | $80,784 | $100,000 | - | - | - | - | - | $80,784 | |
| TOTAL RECOMMENDED | $283,081 | $200,740 |
$88,480
1,118,173
kWh
|
$76,525
-
kW-mo/yr
|
$29,657 |
$6,810
-
gal
|
$825
-
lb
|
$80,784 | ||
| TOTAL IMPLEMENTED | $41,211 | $4,240 |
$8,856
106,823
kWh
|
$20,844
-
kW-mo/yr
|
$11,511 | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs