ITAC Assessment: SD0282
ITAC logo
ITAC Assessment: SD0282
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Automobile wheels
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 350
Plant Area 2,500,000
ft2
Annual Production 3,259,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,368,382 29,998,852
kWh
Electricity Demand $532,691 54,264
kW-mo/yr
Electricity Fees $9,587 -
Natural Gas $5,780,704 711,603
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,522,336 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $173,115

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.2424: Use heat in flue gases to preheat products or materials $2,980,189 $2,980,189 - - $1,887,919
-
MMBtu
- $1,233,270
-
lb
$(-108,000.0) $(-33,000.0) -
02 2.6218: Turn off equipment when not in use $5,953 $190 $5,953
130,550
kWh
- - - - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $103,026 $8,000 $89,153
1,955,117
kWh
$26,373
-
kW-mo/yr
- - - $(-12,500.0) - -
04 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads $6,804 $3,550 $6,804
149,200
kWh
- - - - - - -
05 2.4322: Use or replace with energy efficient substitutes $2,312 $2,000 $1,431
31,389
kWh
$881
-
kW-mo/yr
- - - - - -
06 2.7121: Utilize daylight whenever possible in lieu of artificial light $33,122 $55,000 $12,166
266,800
kWh
$20,956
-
kW-mo/yr
- - - - - -
07 2.2525: Eliminate cooling of process streams which subsequently must be heated and vice versa $55,555 $10,000 - - $55,555
-
MMBtu
- - - - -
08 2.4239: Eliminate or reduce compressed air usage $83,687 $110,000 $58,494
1,282,769
kWh
$25,193
-
kW-mo/yr
- - - - - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,108 $8,000 $2,557
56,070
kWh
$551
-
kW-mo/yr
- - - - - -
10 2.4239: Eliminate or reduce compressed air usage $348,473 $150,000 $243,566
5,341,360
kWh
$104,907
-
kW-mo/yr
- - - - - -
11 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,832,890 $1,400,000 - - - - $1,819,890
-
lb
- $13,000 -
12 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,600 $500 - - - - - - - $5,600
13 3.6193: Install equipment (eg compactor) to reduce disposal costs $21,020 $20,000 - - - - - - - $21,020
14 3.6112: Use filter and drying oven to reduce sludge volume $2,925 $1,500 - - - - - - - $2,925
15 3.3131: Use evaporation to concentrate material $13,681 $3,000 - - - $13,681
-
gal
- - - -
16 4.652: Replace existing equipment with more suitable substitutes $3,022,214 $480,000 - - - - - - $(-180,000.0) $3,202,214
17 4.821: Pay bills on time to avoid late fees $1,777 - - - - - - - - $1,777
TOTAL RECOMMENDED $8,522,336 $5,231,929 $420,124
9,213,255
kWh
$178,861
-
kW-mo/yr
$1,943,474
-
MMBtu
$13,681
-
gal
$3,053,160
-
lb
$(-120,500.0) $(-200,000.0) $3,233,536
TOTAL IMPLEMENTED $173,115 $21,740 $101,910
2,234,867
kWh
$26,373
-
kW-mo/yr
$55,555
-
MMBtu
- - $(-12,500.0) - $1,777
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs