Assessment Year | 2001 |
---|---|
Principal Product | Aluminum coiled sheets and welded tubing |
NAICS |
n/a
|
SIC | 3353: Aluminum Sheet, Plate, and Foil |
Sales Range | $50 M to 100M |
# of Employees | 202 |
Plant Area |
120,000
ft2
|
Annual Production | 46,000,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,103,482 | 23,665,312 |
kWh
|
$0.047 |
Electricity Demand | $591,880 | 58,851 |
kW-mo/yr
|
$10.06 |
Electricity Fees | $7,176 | - |
|
- |
Natural Gas | $2,121,825 | 418,628 |
MMBtu
|
$5.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $480,549 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $170,597 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $126,144 | $15,000 | n/a | - | - |
$126,144
-
MMBtu
|
- | - | - |
02 | 2.2424: Use heat in flue gases to preheat products or materials | $37,083 | $40,000 | n/a | - | - |
$37,083
-
MMBtu
|
- | - | - |
03 | 2.2437: Recover waste heat from equipment | $48,575 | $10,000 | - | - |
$48,575
-
MMBtu
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,911 | $440 |
$6,090
130,689
kWh
|
$1,821
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.3137: Use power during off-peak periods | $36,091 | - | - |
$36,091
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7145: Install skylights | $18,319 | $50,000 |
$8,380
179,831
kWh
|
$9,939
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $1,712 | $1,000 |
$1,075
23,063
kWh
|
$637
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,260 | $8,000 |
$2,760
59,237
kWh
|
$500
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.2211: Use optimum temperature | $4,364 | - |
$4,364
93,639
kWh
|
- | - | - | - | - | |
10 | 2.4239: Eliminate or reduce compressed air usage | $11,682 | $2,300 |
$8,159
175,091
kWh
|
$3,523
-
kW-mo/yr
|
- | - | - | - | |
11 | 3.4131: Minimize contamination of water before treatment | $83,208 | $2,000 | - | - | - |
$83,208
-
gal
|
- | - | |
12 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $25,500 | $20,000 | - | - | - | - | $(-500.0) | $26,000 | |
13 | 4.821: Pay bills on time to avoid late fees | $3,379 | - | - | - | - | - | $3,379 | - | |
14 | 4.454: Modify startup/shutdown times | $73,321 | - | - |
$73,321
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $480,549 | $148,740 |
$30,828
661,550
kWh
|
$125,832
-
kW-mo/yr
|
$211,802
-
MMBtu
|
$83,208
-
gal
|
$2,879 | $26,000 | ||
TOTAL IMPLEMENTED | $170,597 | $71,440 |
$19,909
427,222
kWh
|
$121,809
-
kW-mo/yr
|
- | - | $2,879 | $26,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs