ITAC Assessment: SD0265
ITAC logo
ITAC Assessment: SD0265
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product naval ship repairs
NAICS
n/a
SIC 3731: Ship Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 230,000
ft2
Annual Production 50
pieces
Production Hrs. Annual 2,168
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $70,737 817,000
kWh
Electricity Demand $24,440 3,055
kW-mo/yr
Electricity Fees $520 -
Natural Gas $3,612 458
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,675 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,267

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,388 $500 $2,901
33,499
kWh
$1,487
-
kW-mo/yr
- - -
02 2.4239: Eliminate or reduce compressed air usage $6,625 $13,000 $5,193
59,970
kWh
$1,432
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,234 $460 $817
9,430
kWh
$417
-
kW-mo/yr
- - -
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,874 $1,012 $1,087
12,546
kWh
$787
-
kW-mo/yr
- - -
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $4,783 $12,500 - - - $4,783 -
06 3.7311: Maintain machines to reduce leaks $1,771 - - - $833
-
lb
- $938
TOTAL RECOMMENDED $20,675 $27,472 $9,998
115,445
kWh
$4,123
-
kW-mo/yr
$833
-
lb
$4,783 $938
TOTAL IMPLEMENTED $9,267 $1,972 $4,805
55,475
kWh
$2,691
-
kW-mo/yr
$833
-
lb
- $938
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs