Assessment Year | 2001 |
---|---|
Principal Product | naval ship repairs |
NAICS |
n/a
|
SIC | 3731: Ship Building and Repairing |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
230,000
ft2
|
Annual Production | 50
pieces
|
Production Hrs. Annual | 2,168
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,737 | 817,000 |
kWh
|
$0.087 |
Electricity Demand | $24,440 | 3,055 |
kW-mo/yr
|
$8.00 |
Electricity Fees | $520 | - |
|
- |
Natural Gas | $3,612 | 458 |
MMBtu
|
$7.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,267 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,388 | $500 |
$2,901
33,499
kWh
|
$1,487
-
kW-mo/yr
|
- | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $6,625 | $13,000 |
$5,193
59,970
kWh
|
$1,432
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,234 | $460 |
$817
9,430
kWh
|
$417
-
kW-mo/yr
|
- | - | - | |
04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,874 | $1,012 |
$1,087
12,546
kWh
|
$787
-
kW-mo/yr
|
- | - | - | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,783 | $12,500 | - | - | - | $4,783 | - | |
06 | 3.7311: Maintain machines to reduce leaks | $1,771 | - | - | - |
$833
-
lb
|
- | $938 | |
TOTAL RECOMMENDED | $20,675 | $27,472 |
$9,998
115,445
kWh
|
$4,123
-
kW-mo/yr
|
$833
-
lb
|
$4,783 | $938 | ||
TOTAL IMPLEMENTED | $9,267 | $1,972 |
$4,805
55,475
kWh
|
$2,691
-
kW-mo/yr
|
$833
-
lb
|
- | $938 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs