ITAC Assessment: SD0254
ITAC logo
ITAC Assessment: SD0254
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Magnesium castings
NAICS
n/a
SIC 3365: Aluminum Foundries
Sales Range $10
M
to 50
M
# of Employees 42
Plant Area 180,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,125
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,039 648,886
kWh
Electricity Demand $33,409 3,852
kW-mo/yr
Electricity Fees $2,375 -
Natural Gas $15,672 4,679
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $136,374 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,285

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $22,489 $70,000 $13,890
163,834
kWh
$10,802
-
kW-mo/yr
$(-2,203.0)
-
MMBtu
- - - -
02 2.7132: Install timers on light switches in little used areas $5,944 $720 $5,944
70,047
kWh
- - - - - -
03 2.4322: Use or replace with energy efficient substitutes $1,974 - $1,974
23,154
kWh
- - - - - -
04 2.4322: Use or replace with energy efficient substitutes $1,675 - - - $1,675
-
MMBtu
- - - -
05 3.5221: Recycle casting sand $90,000 $120,000 - - - - $90,000
-
lb
- -
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,700 $5,400 - - - $1,700
-
lb
- - -
07 4.445: Install equipment to move product $10,600 $23,000 - - - - - $10,600 -
08 4.521: Clear and rent existing space $1,992 - - - - - - - $1,992
TOTAL RECOMMENDED $136,374 $219,120 $21,808
257,035
kWh
$10,802
-
kW-mo/yr
$(-528.0)
-
MMBtu
$1,700
-
lb
$90,000
-
lb
$10,600 $1,992
TOTAL IMPLEMENTED $13,285 $6,120 $7,918
93,201
kWh
- $1,675
-
MMBtu
$1,700
-
lb
- - $1,992
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs