| Assessment Year | 2000 |
|---|---|
| Principal Product | Magnesium castings |
| NAICS |
n/a
|
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 42 |
| Plant Area |
180,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,039 | 648,886 |
kWh
|
$0.085 |
| Electricity Demand | $33,409 | 3,852 |
kW-mo/yr
|
$8.67 |
| Electricity Fees | $2,375 | - |
|
- |
| Natural Gas | $15,672 | 4,679 |
MMBtu
|
$3.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $136,374 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,285 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $22,489 | $70,000 |
$13,890
163,834
kWh
|
$10,802
-
kW-mo/yr
|
$(-2,203.0)
-
MMBtu
|
- | - | - | - | |
| 02 | 2.7132: Install timers on light switches in little used areas | $5,944 | $720 |
$5,944
70,047
kWh
|
- | - | - | - | - | - | |
| 03 | 2.4322: Use or replace with energy efficient substitutes | $1,974 | - |
$1,974
23,154
kWh
|
- | - | - | - | - | - | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $1,675 | - | - | - |
$1,675
-
MMBtu
|
- | - | - | - | |
| 05 | 3.5221: Recycle casting sand | $90,000 | $120,000 | - | - | - | - |
$90,000
-
lb
|
- | - | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,700 | $5,400 | - | - | - |
$1,700
-
lb
|
- | - | - | |
| 07 | 4.445: Install equipment to move product | $10,600 | $23,000 | - | - | - | - | - | $10,600 | - | |
| 08 | 4.521: Clear and rent existing space | $1,992 | - | - | - | - | - | - | - | $1,992 | |
| TOTAL RECOMMENDED | $136,374 | $219,120 |
$21,808
257,035
kWh
|
$10,802
-
kW-mo/yr
|
$(-528.0)
-
MMBtu
|
$1,700
-
lb
|
$90,000
-
lb
|
$10,600 | $1,992 | ||
| TOTAL IMPLEMENTED | $13,285 | $6,120 |
$7,918
93,201
kWh
|
- |
$1,675
-
MMBtu
|
$1,700
-
lb
|
- | - | $1,992 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs