| Assessment Year | 2000 |
|---|---|
| Principal Product | aluminum castings |
| NAICS |
n/a
|
| SIC | 3365: Aluminum Foundries |
| Sales Range | $5 M to 10M |
| # of Employees | 130 |
| Plant Area |
72,000
ft2
|
| Annual Production | 420,000
lb
|
| Production Hrs. Annual | 4,080
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $130,022 | 2,001,172 |
kWh
|
$0.065 |
| Electricity Demand | $85,634 | 7,197 |
kW-mo/yr
|
$11.90 |
| Electricity Fees | $4,483 | - |
|
- |
| Natural Gas | $98,479 | 27,583 |
MMBtu
|
$3.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $179,961 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $108,760 | $68,000 |
$74,190
1,141,852
kWh
|
$53,264
-
kW-mo/yr
|
$(-18,694.0)
-
MMBtu
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $14,706 | $15,000 |
$5,801
89,390
kWh
|
$10,195
-
kW-mo/yr
|
$(-1,290.0)
-
MMBtu
|
- | - | |
| 03 | 2.4323: Use optimum size and capacity equipment | $20,080 | $25,000 | - | - |
$20,080
-
MMBtu
|
- | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,561 | $12,000 |
$8,561
131,887
kWh
|
- | - | - | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $2,622 | $7,000 | - | - |
$2,622
-
MMBtu
|
- | - | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,732 | $5,400 | - | - | - |
$2,732
-
lb
|
- | |
| 07 | 4.424: Improve space comfort conditioning | $22,500 | $15,000 | - | - | - | - | $22,500 | |
| TOTAL RECOMMENDED | $179,961 | $147,400 |
$88,552
1,363,129
kWh
|
$63,459
-
kW-mo/yr
|
$2,718
-
MMBtu
|
$2,732
-
lb
|
$22,500 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs