ITAC Assessment: SD0252
ITAC logo
ITAC Assessment: SD0252
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product personal hygiene products
NAICS
n/a
SIC 2834: Pharmaceutical Preparations
Sales Range $10
M
to 50
M
# of Employees 435
Plant Area 650,000
ft2
Annual Production 25,000
ton
Production Hrs. Annual 7,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $126,435 5,186,987
kWh
Electricity Demand $91,155 9,659
kW-mo/yr
Electricity Fees $1,920 -
Natural Gas $173,005 47,687
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $400,474 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $129,234

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2121: Increase amount of condensate returned $36,908 $85,000 - - $29,150
-
MMBtu
$7,758
-
Tgal
- - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $12,800 $40,000 $7,027
288,101
kWh
$10,195
-
kW-mo/yr
$(-4,422.0)
-
MMBtu
- - - -
03 2.2427: Use waste heat from hot flue gases to preheat incoming fluids $9,331 $20,000 - - $9,331
-
MMBtu
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,867 $200 $3,567
146,249
kWh
$2,300
-
kW-mo/yr
- - - - -
05 2.4131: Size electric motors for peak operating efficiency $4,167 $10,200 $1,467
60,082
kWh
$2,700
-
kW-mo/yr
- - - - -
06 2.4239: Eliminate or reduce compressed air usage $2,692 $1,500 $2,692
110,492
kWh
- - - - - -
07 2.7145: Install skylights $70,269 $5,536 - $1,269
-
kW-mo/yr
- - - - $69,000
08 3.5316: Contract a wood pallet recycling company $2,240 $30,000 - - - - - $2,240 -
09 4.112: Replace old machine with new automatic multi-station tool $256,200 $100,000 - - - - $256,200 - -
TOTAL RECOMMENDED $400,474 $292,436 $14,753
604,924
kWh
$16,464
-
kW-mo/yr
$34,059
-
MMBtu
$7,758
-
Tgal
$256,200 $2,240 $69,000
TOTAL IMPLEMENTED $129,234 $122,436 $7,726
316,823
kWh
$6,269
-
kW-mo/yr
$38,481
-
MMBtu
$7,758
-
Tgal
- - $69,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs