Assessment Year | 2000 |
---|---|
Principal Product | Aluminum extrusion |
NAICS |
n/a
|
SIC | 3354: Aluminum Extruded Products |
Sales Range | $10 M to 50M |
# of Employees | 380 |
Plant Area |
216,000
ft2
|
Annual Production | 20,000
ton
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,109,226 | 24,573,857 |
kWh
|
$0.045 |
Electricity Demand | $437,274 | 42,567 |
kW-mo/yr
|
$10.27 |
Electricity Fees | $3,588 | - |
|
- |
Natural Gas | $1,360,222 | 421,389 |
MMBtu
|
$3.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $366,557 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,752 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $45,106 | $210,000 |
$45,106
998,242
kWh
|
$13,747
-
kW-mo/yr
|
$(-13,747.0)
-
MMBtu
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $44,752 | $600 |
$38,845
859,613
kWh
|
$18,387
-
kW-mo/yr
|
- | - | - | $(-12,480.0) | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,942 | $4,100 |
$1,633
36,049
kWh
|
$309
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2628: Utilize a less expensive cooling method | $8,901 | $40,000 |
$6,474
143,318
kWh
|
$2,427
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $3,256 | $8,000 | - | - |
$3,256
-
MMBtu
|
- | - | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $148,200 | $8,000 | - | - | - | - |
$148,200
-
gal
|
- | |
07 | 3.4111: Use closed cycle process to minimize waste water production | $97,460 | $135,000 | - | - | - |
$97,460
-
Tgal
|
- | - | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $11,240 | $7,900 | - | - | - | - | - | $11,240 | |
09 | 3.6112: Use filter and drying oven to reduce sludge volume | $5,000 | $12,500 | - | - | - | - | - | $5,000 | |
10 | 3.8136: Switch to a solvent that can be cleaned and re-used | $700 | - | - | - | - | - | - | $700 | |
TOTAL RECOMMENDED | $366,557 | $426,100 |
$92,058
2,037,222
kWh
|
$34,870
-
kW-mo/yr
|
$(-10,491.0)
-
MMBtu
|
$97,460
-
Tgal
|
$148,200
-
gal
|
$4,460 | ||
TOTAL IMPLEMENTED | $44,752 | $600 |
$38,845
859,613
kWh
|
$18,387
-
kW-mo/yr
|
- | - | - | $(-12,480.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs