Assessment Year | 2000 |
---|---|
Principal Product | slot machine cases |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
65,000
ft2
|
Annual Production | 2,000,000
lb
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,352 | 924,385 |
kWh
|
$0.057 |
Electricity Demand | $42,471 | 3,559 |
kW-mo/yr
|
$11.93 |
Electricity Fees | $1,044 | - |
|
- |
Natural Gas | $26,510 | 5,012 |
MMBtu
|
$5.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $71,141 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2425: Use flue gases to heat process or service water | $11,396 | $8,250 | - | - |
$11,396
-
MMBtu
|
- | |
02 | 2.4226: Use / purchase optimum sized compressor | $6,905 | $3,000 |
$3,701
65,358
kWh
|
$3,204
-
kW-mo/yr
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,007 | - |
$2,472
43,669
kWh
|
$535
-
kW-mo/yr
|
- | - | |
04 | 2.2612: Use cooling tower water instead of refrigeration | $5,628 | $3,000 |
$4,060
71,805
kWh
|
$1,568
-
kW-mo/yr
|
- | - | |
05 | 2.7224: Reduce space conditioning during non-working hours | $1,279 | $1,800 |
$1,279
22,567
kWh
|
- | - | - | |
06 | 2.2511: Insulate bare equipment | $570 | $1,030 | - | - |
$570
-
MMBtu
|
- | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,440 | $12,500 | - | - | - | $3,440 | |
08 | 3.5316: Contract a wood pallet recycling company | $6,916 | - | - | - | - | $6,916 | |
09 | 4.424: Improve space comfort conditioning | $32,000 | $10,380 | - | - | - | $32,000 | |
TOTAL RECOMMENDED | $71,141 | $39,960 |
$11,512
203,399
kWh
|
$5,307
-
kW-mo/yr
|
$11,966
-
MMBtu
|
$42,356 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs