ITAC Assessment: SD0239
ITAC logo
ITAC Assessment: SD0239
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product sailboats
NAICS
n/a
SIC 3732: Boat Building and Repairing
Sales Range $5
M
to 10
M
# of Employees 120
Plant Area 74,000
ft2
Annual Production 900
pieces
Production Hrs. Annual 4,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,166 400,352
kWh
Electricity Demand $13,978 1,921
kW-mo/yr
Electricity Fees $2,280 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $100,121 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,216

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7224: Reduce space conditioning during non-working hours $1,960 $300 $1,960
24,326
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $4,716 - $3,751
46,600
kWh
$965
-
kW-mo/yr
-
03 3.2121: Convert to electrostatic powder coating $7,470 $56,000 - - $7,470
04 4.431: Train operators for maximum operating efficiency $45,475 $66,000 - - $45,475
05 4.424: Improve space comfort conditioning $40,500 $7,500 - - $40,500
TOTAL RECOMMENDED $100,121 $129,800 $5,711
70,926
kWh
$965
-
kW-mo/yr
$93,445
TOTAL IMPLEMENTED $45,216 $7,500 $3,751
46,600
kWh
$965
-
kW-mo/yr
$40,500
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs