ITAC Assessment: SD0238
ITAC logo
ITAC Assessment: SD0238
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product combustible ordinances
NAICS
n/a
SIC 3483: Ammunition, Except for Small Arms
Sales Range $10
M
to 50
M
# of Employees 240
Plant Area 108,000
ft2
Annual Production 600,000
pieces
Production Hrs. Annual 4,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $436,048 6,618,406
kWh
Electricity Demand $54,249 19,152
kW-mo/yr
Electricity Fees $25,505 -
Natural Gas $160,412 94,741
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $428,143 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $61,356

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings
01 2.2422: Use waste heat from hot flue gases to generate steam $21,910 $10,250 - - $21,910
-
MMBtu
- -
02 2.2422: Use waste heat from hot flue gases to generate steam $13,294 $11,825 - - $13,294
-
MMBtu
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $838 $1,880 $792
11,430
kWh
$46
-
kW-mo/yr
- - -
04 3.6192: Use a less expensive method of waste removal $171,427 $100,000 - - $45,427
-
MMBtu
- $126,000
05 3.4111: Use closed cycle process to minimize waste water production $25,314 $100,000 - - - $25,314
-
Tgal
-
06 4.111: Add equipment/ operators to reduce production bottleneck $188,160 $200,000 - - - - $188,160
07 4.111: Add equipment/ operators to reduce production bottleneck $7,200 $3,000 - - - - $7,200
TOTAL RECOMMENDED $428,143 $426,955 $792
11,430
kWh
$46
-
kW-mo/yr
$80,631
-
MMBtu
$25,314
-
Tgal
$321,360
TOTAL IMPLEMENTED $61,356 $123,955 $792
11,430
kWh
$46
-
kW-mo/yr
$35,204
-
MMBtu
$25,314
-
Tgal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs