| Assessment Year | 2000 |
|---|---|
| Principal Product | combustible ordinances |
| NAICS |
n/a
|
| SIC | 3483: Ammunition, Except for Small Arms |
| Sales Range | $10 M to 50M |
| # of Employees | 240 |
| Plant Area |
108,000
ft2
|
| Annual Production | 600,000
pieces
|
| Production Hrs. Annual | 4,200
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $436,048 | 6,618,406 |
kWh
|
$0.066 |
| Electricity Demand | $54,249 | 19,152 |
kW-mo/yr
|
$2.83 |
| Electricity Fees | $25,505 | - |
|
- |
| Natural Gas | $160,412 | 94,741 |
MMBtu
|
$1.69 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $428,143 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $61,356 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2422: Use waste heat from hot flue gases to generate steam | $21,910 | $10,250 | - | - |
$21,910
-
MMBtu
|
- | - | |
| 02 | 2.2422: Use waste heat from hot flue gases to generate steam | $13,294 | $11,825 | - | - |
$13,294
-
MMBtu
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $838 | $1,880 |
$792
11,430
kWh
|
$46
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.6192: Use a less expensive method of waste removal | $171,427 | $100,000 | - | - |
$45,427
-
MMBtu
|
- | $126,000 | |
| 05 | 3.4111: Use closed cycle process to minimize waste water production | $25,314 | $100,000 | - | - | - |
$25,314
-
Tgal
|
- | |
| 06 | 4.111: Add equipment/ operators to reduce production bottleneck | $188,160 | $200,000 | - | - | - | - | $188,160 | |
| 07 | 4.111: Add equipment/ operators to reduce production bottleneck | $7,200 | $3,000 | - | - | - | - | $7,200 | |
| TOTAL RECOMMENDED | $428,143 | $426,955 |
$792
11,430
kWh
|
$46
-
kW-mo/yr
|
$80,631
-
MMBtu
|
$25,314
-
Tgal
|
$321,360 | ||
| TOTAL IMPLEMENTED | $61,356 | $123,955 |
$792
11,430
kWh
|
$46
-
kW-mo/yr
|
$35,204
-
MMBtu
|
$25,314
-
Tgal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs