| Assessment Year | 1999 |
|---|---|
| Principal Product | Medical devices for surgery |
| NAICS |
n/a
|
| SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
| Sales Range | $10 M to 50M |
| # of Employees | 315 |
| Plant Area |
57,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,125
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,449 | 1,091,149 |
kWh
|
$0.079 |
| Electricity Demand | $34,940 | 2,405 |
kW-mo/yr
|
$14.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $189,154 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,069 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,609 | $25,688 |
$13,552
171,161
kWh
|
$6,057
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7144: Install spectral reflectors / delamp | $26,750 | $21,265 |
$18,486
233,294
kWh
|
$8,264
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $6,768 | $13,000 |
$4,458
56,272
kWh
|
$2,310
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,069 | $1,425 |
$558
7,034
kWh
|
$511
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,471 | $7,825 |
$1,625
20,516
kWh
|
$846
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,739 | $3,334 |
$2,281
28,722
kWh
|
$2,511
-
kW-mo/yr
|
$(-1,053.0)
-
MMBtu
|
- | - | |
| 07 | 2.4239: Eliminate or reduce compressed air usage | $151 | - |
$41
586
kWh
|
$110
-
kW-mo/yr
|
- | - | - | |
| 08 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $8,640 | $510 | - | - | - | - | $8,640 | |
| 09 | 4.445: Install equipment to move product | $119,957 | $150,000 | - | - | - | $119,957 | - | |
| TOTAL RECOMMENDED | $189,154 | $223,047 |
$41,001
517,585
kWh
|
$20,609
-
kW-mo/yr
|
$(-1,053.0)
-
MMBtu
|
$119,957 | $8,640 | ||
| TOTAL IMPLEMENTED | $1,069 | $1,425 |
$558
7,034
kWh
|
$511
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs