Assessment Year | 1995 |
---|---|
Principal Product | Fabricated metal parts - farm machinery |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
56,000
ft2
|
Annual Production | 1,800
ton
|
Production Hrs. Annual | 3,536
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,142 | 919,695 |
kWh
|
$0.060 |
LPG | $9,437 | 1,507 |
MMBtu
|
$6.26 |
Fuel Oil #2 | $18,898 | 3,599 |
MMBtu
|
$5.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,530 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,990 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,210 | $15,710 |
$4,210
70,633
kWh
|
- | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $3,900 | $38,110 |
$3,900
65,064
kWh
|
- | - | |
03 | 3.8125: Remove rollers from the machines and clean in a closed solvent cleaner | $640 | $1,000 | - |
$330
-
gal
|
$310 | |
04 | 3.8142: Distill contaminated solvents for reuse | $940 | $4,850 |
$(-40.0)
(-586)
kWh
|
$400
-
gal
|
$580 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $520 | $210 |
$520
8,792
kWh
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $320 | $280 |
$320
5,275
kWh
|
- | - | |
TOTAL RECOMMENDED | $10,530 | $60,160 |
$8,910
149,178
kWh
|
$730
-
gal
|
$890 | ||
TOTAL IMPLEMENTED | $5,990 | $21,050 |
$5,010
84,114
kWh
|
$400
-
gal
|
$580 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs