Assessment Year | 1999 |
---|---|
Principal Product | Latches and hinges |
NAICS |
n/a
|
SIC | 3429: Hardware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
50,000
ft2
|
Annual Production | 40,000
lb
|
Production Hrs. Annual | 5,125
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $98,094 | 1,276,084 |
kWh
|
$0.077 |
Electricity Demand | $39,101 | 4,397 |
kW-mo/yr
|
$8.89 |
Electricity Fees | $727 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $139,679 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,917 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,875 | $2,988 |
$4,623
60,082
kWh
|
$1,252
-
kW-mo/yr
|
- | - | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $13,528 | $10,000 |
$7,075
92,028
kWh
|
$9,815
-
kW-mo/yr
|
$(-3,362.0)
-
MMBtu
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,665 | $500 |
$1,850
24,033
kWh
|
$815
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,377 | $120 |
$2,581
31,360
kWh
|
$796
-
kW-mo/yr
|
- | - | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $13,502 | $11,000 |
$7,682
99,941
kWh
|
$9,473
-
kW-mo/yr
|
$(-3,653.0)
-
MMBtu
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $1,372 | $540 | - | - | - |
$1,372
-
gal
|
- | |
07 | 4.651: Install back-up equipment | $23,040 | $15,000 | - | - | - | - | $23,040 | |
08 | 4.445: Install equipment to move product | $76,320 | $30,000 | - | - | - | - | $76,320 | |
TOTAL RECOMMENDED | $139,679 | $70,148 |
$23,811
307,444
kWh
|
$22,151
-
kW-mo/yr
|
$(-7,015.0)
-
MMBtu
|
$1,372
-
gal
|
$99,360 | ||
TOTAL IMPLEMENTED | $11,917 | $3,608 |
$9,054
115,475
kWh
|
$2,863
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs