Assessment Year | 1999 |
---|---|
Principal Product | Plastic products |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 112 |
Plant Area |
45,000
ft2
|
Annual Production | 1,500,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,701 | 1,778,136 |
kWh
|
$0.068 |
Electricity Demand | $32,059 | 3,940 |
kW-mo/yr
|
$8.14 |
Natural Gas | $579 | 81 |
MMBtu
|
$7.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $90,592 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,839 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,751 | $4,040 |
$1,320
19,343
kWh
|
$431
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7144: Install spectral reflectors / delamp | $1,824 | $2,400 |
$1,375
20,223
kWh
|
$449
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,129 | $50 |
$917
13,482
kWh
|
$212
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,584 | $400 |
$1,261
18,464
kWh
|
$323
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $488 | $800 |
$438
6,448
kWh
|
$50
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,751 | - |
$1,420
20,809
kWh
|
$2,331
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $73,351 | $169,125 |
$61,724
907,972
kWh
|
$11,627
-
kW-mo/yr
|
- | - | - | - | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $903 | - | - | - | - | - | - | $903 | |
09 | 3.5217: Reuse / recycle/ sell paper products | $1,618 | - | - | - | - | - |
$1,618
-
lb
|
- | |
10 | 3.8133: Convert to aqueous cleaning | $1,362 | - | - | - | - |
$1,362
-
gal
|
- | - | |
11 | 3.7311: Maintain machines to reduce leaks | $1,103 | $385 | - | - |
$1,103
-
Tgal
|
- | - | - | |
12 | 4.651: Install back-up equipment | $1,728 | - | - | - | - | - | - | $1,728 | |
TOTAL RECOMMENDED | $90,592 | $177,200 |
$68,455
1,006,741
kWh
|
$15,423
-
kW-mo/yr
|
$1,103
-
Tgal
|
$1,362
-
gal
|
$1,618
-
lb
|
$2,631 | ||
TOTAL IMPLEMENTED | $11,839 | $4,875 |
$4,918
72,098
kWh
|
$3,297
-
kW-mo/yr
|
$1,103
-
Tgal
|
- |
$1,618
-
lb
|
$903 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs