Assessment Year | 1999 |
---|---|
Principal Product | Heat Exchangers |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
120,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 4,676
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $178,393 | 2,652,403 |
kWh
|
$0.067 |
Electricity Demand | $42,948 | 5,816 |
kW-mo/yr
|
$7.38 |
Natural Gas | $10,883 | 1,799 |
MMBtu
|
$6.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $155,041 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,069 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,040 | $5,528 |
$8,721
129,543
kWh
|
$2,319
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,440 | $500 |
$2,564
38,101
kWh
|
$876
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $55,972 | $80,000 |
$48,393
719,226
kWh
|
$7,579
-
kW-mo/yr
|
- | - | |
04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $17,838 | $732 | - | - |
$17,838
-
gal
|
- | |
05 | 3.8133: Convert to aqueous cleaning | $7,548 | - | - | - |
$7,548
-
gal
|
- | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,710 | $8,500 | - | - | - |
$7,710
-
lb
|
|
07 | 4.114: Add/modify equipment to improve drying process | $51,493 | $8,000 |
$45,547
677,022
kWh
|
$5,946
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $155,041 | $103,260 |
$105,225
1,563,892
kWh
|
$16,720
-
kW-mo/yr
|
$25,386
-
gal
|
$7,710
-
lb
|
||
TOTAL IMPLEMENTED | $99,069 | $23,260 |
$56,832
844,666
kWh
|
$9,141
-
kW-mo/yr
|
$25,386
-
gal
|
$7,710
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs