Assessment Year | 1999 |
---|---|
Principal Product | electronic enclosures |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 115 |
Plant Area |
60,000
ft2
|
Annual Production | 2,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $44,212 | 608,148 |
kWh
|
$0.073 |
Electricity Demand | $12,039 | 2,031 |
kW-mo/yr
|
$5.93 |
Electricity Fees | $3,465 | - |
|
- |
Natural Gas | $6,947 | 2,383 |
MMBtu
|
$2.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $206,416 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $163,290 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7144: Install spectral reflectors / delamp | $1,485 | $1,420 |
$1,148
15,826
kWh
|
$337
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $953 | $2,268 |
$733
9,965
kWh
|
$220
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,351 | $300 |
$2,692
36,928
kWh
|
$659
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,614 | $500 |
$4,901
67,409
kWh
|
$1,713
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $1,938 | $3,800 | - | - |
$1,938
-
MMBtu
|
- | - | - | - | - | - | |
06 | 2.7145: Install skylights | $520 | $1,380 |
$349
4,689
kWh
|
$171
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
07 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $6,059 | $1,000 | - | - |
$4,897
-
MMBtu
|
- | - | - | - |
$1,162
-
Tgal
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,136 | $400 |
$2,332
32,239
kWh
|
$804
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
09 | 2.6218: Turn off equipment when not in use | $9,689 | $1,195 |
$9,689
979,191
kWh
|
- | - | - | - | - | - | - | - | |
10 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,680 | - | - | - | - | - |
$1,680
-
lb
|
- | - | - | - | |
11 | 3.2121: Convert to electrostatic powder coating | $147,960 | $10,000 | - | - | - |
$75,960
-
gal
|
- | - | $72,000 | - | - | |
12 | 4.441: Install automatic packing equipment | $4,000 | $8,000 | - | - | - | - | - | $4,000 | - | - | - | |
13 | 4.514: Re-arrange equipment layout to reduce handling costs | $12,000 | $21,920 | - | - | - | - | - | $12,000 | - | - | - | |
14 | 3.4151: Minimize water usage | $1,451 | - | - | - | - | - | - | $967 | - | - | $484 | |
15 | 3.6192: Use a less expensive method of waste removal | $5,580 | - | - | - | - | - | - | $3,720 | - | - | $1,860 | |
TOTAL RECOMMENDED | $206,416 | $52,183 |
$21,844
1,146,247
kWh
|
$3,904
-
kW-mo/yr
|
$6,835
-
MMBtu
|
$75,960
-
gal
|
$1,680
-
lb
|
$20,687 | $72,000 |
$1,162
-
Tgal
|
$2,344 | ||
TOTAL IMPLEMENTED | $163,290 | $10,900 |
$7,233
99,648
kWh
|
$2,517
-
kW-mo/yr
|
- |
$75,960
-
gal
|
- | $3,720 | $72,000 | - | $1,860 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs