Assessment Year | 1998 |
---|---|
Principal Product | Couplers |
NAICS |
n/a
|
SIC | 3644: Noncurrent-Carrying Wiring Devices |
Sales Range | $10 M to 50M |
# of Employees | 42 |
Plant Area |
38,100
ft2
|
Annual Production | 14,000,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,967 | 689,039 |
kWh
|
$0.077 |
Electricity Demand | $29,502 | 3,199 |
kW-mo/yr
|
$9.22 |
Natural Gas | $31,247 | 5,779 |
MMBtu
|
$5.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,261 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $901 | - |
$541
7,034
kWh
|
$360
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,500 | $36,250 |
$4,780
62,134
kWh
|
$2,720
-
kW-mo/yr
|
- | |
03 | 4.111: Add equipment/ operators to reduce production bottleneck | $8,860 | $3,100 | - | - | $8,860 | |
TOTAL RECOMMENDED | $17,261 | $39,350 |
$5,321
69,168
kWh
|
$3,080
-
kW-mo/yr
|
$8,860 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs