| Assessment Year | 1998 |
|---|---|
| Principal Product | Aerospace and automotive seals |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
60,000
ft2
|
| Annual Production | 500,000
pieces
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $153,880 | 1,527,257 |
kWh
|
$0.10 |
| Electricity Demand | $37,018 | 4,191 |
kW-mo/yr
|
$8.83 |
| Natural Gas | $3,158 | 442 |
MMBtu
|
$7.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $106,011 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,146 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,582 | $750 |
$1,247
16,413
kWh
|
$335
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $2,572 | $4,900 |
$1,589
20,809
kWh
|
$983
-
kW-mo/yr
|
- | - | |
| 03 | 2.2442: Preheat combustion air with waste heat | $2,756 | $1,182 | - | - |
$2,756
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,118 | $16,039 |
$4,574
60,082
kWh
|
$1,544
-
kW-mo/yr
|
- | - | |
| 05 | 2.7144: Install spectral reflectors / delamp | $17,565 | $11,460 |
$13,622
179,367
kWh
|
$3,943
-
kW-mo/yr
|
- | - | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,118 | $8,500 | - | - | - | $4,118 | |
| 07 | 3.1161: Eliminate/reduce an operation | $71,300 | - | - | - | - | $71,300 | |
| TOTAL RECOMMENDED | $106,011 | $42,831 |
$21,032
276,671
kWh
|
$6,805
-
kW-mo/yr
|
$2,756
-
MMBtu
|
$75,418 | ||
| TOTAL IMPLEMENTED | $17,146 | $31,371 |
$7,410
97,304
kWh
|
$2,862
-
kW-mo/yr
|
$2,756
-
MMBtu
|
$4,118 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs