ITAC Assessment: SD0197
ITAC logo
ITAC Assessment: SD0197
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Fluid handling products
NAICS
n/a
SIC 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products
Sales Range $10
M
to 50
M
# of Employees 270
Plant Area 93,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 5,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $271,287 4,557,737
kWh
Electricity Demand $127,355 10,011
kW-mo/yr
Natural Gas $53,461 10,471
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,695 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,082

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $3,252 $2,520 $1,902
31,653
kWh
$1,350
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,569 $350 $2,686
30,188
kWh
$883
-
kW-mo/yr
- - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,535 $2,000 $1,099
11,137
kWh
$436
-
kW-mo/yr
- - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $18,682 $7,000 $14,423
157,972
kWh
$4,946
-
kW-mo/yr
$(-687.0)
-
MMBtu
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $17,149 $23,968 $11,502
191,676
kWh
$5,647
-
kW-mo/yr
- - -
06 2.7144: Install spectral reflectors / delamp $13,931 $10,620 $9,555
159,437
kWh
$4,376
-
kW-mo/yr
- - -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $12,516 $2,000 - - - $12,516
-
lb
-
08 3.7134: Wash and reuse rags on-site $711 $600 - - - $711
-
lb
-
09 4.112: Replace old machine with new automatic multi-station tool $1,350 $1,000 - - - - $1,350
TOTAL RECOMMENDED $72,695 $50,058 $41,167
582,063
kWh
$17,638
-
kW-mo/yr
$(-687.0)
-
MMBtu
$13,227
-
lb
$1,350
TOTAL IMPLEMENTED $40,082 $32,438 $17,189
264,654
kWh
$8,316
-
kW-mo/yr
- $13,227
-
lb
$1,350
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs