Assessment Year | 1998 |
---|---|
Principal Product | PCB Containers, and Heat Sinks |
NAICS |
n/a
|
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
80,000
ft2
|
Annual Production | 75,000
thousand feet
|
Production Hrs. Annual | 3,850
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $119,958 | 1,482,708 |
kWh
|
$0.081 |
Electricity Demand | $44,350 | 5,016 |
kW-mo/yr
|
$8.84 |
Natural Gas | $4,435 | 608 |
MMBtu
|
$7.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,490 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,374 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $3,625 | $5,210 |
$2,518
31,067
kWh
|
$1,107
-
kW-mo/yr
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $20,551 | $10,500 |
$17,963
221,864
kWh
|
$3,629
-
kW-mo/yr
|
$(-1,041.0)
-
MMBtu
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $2,430 | $450 |
$1,538
19,050
kWh
|
$892
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $706 | $1,150 |
$527
6,448
kWh
|
$179
-
kW-mo/yr
|
- | - | |
05 | 2.2515: Use optimum thickness insulation | $2,213 | $1,559 | - |
$561
-
kW-mo/yr
|
$1,652
-
MMBtu
|
- | |
06 | 2.7144: Install spectral reflectors / delamp | $3,975 | $7,590 |
$2,494
30,774
kWh
|
$1,481
-
kW-mo/yr
|
- | - | |
07 | 3.5242: Recover metals from spent solutions and recycle | $2,400 | $1,000 | - | - | - | $2,400 | |
08 | 3.2171: Use an automatic plate processor | $4,590 | $1,000 | - | - | - | $4,590 | |
TOTAL RECOMMENDED | $40,490 | $28,459 |
$25,040
309,203
kWh
|
$7,849
-
kW-mo/yr
|
$611
-
MMBtu
|
$6,990 | ||
TOTAL IMPLEMENTED | $11,374 | $9,369 |
$4,583
56,565
kWh
|
$2,739
-
kW-mo/yr
|
$1,652
-
MMBtu
|
$2,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs