Assessment Year | 1998 |
---|---|
Principal Product | Commercial Refrigerants |
NAICS |
n/a
|
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 100 |
Plant Area |
1,000,000
ft2
|
Annual Production | 75,000,000
lb
|
Production Hrs. Annual | 8,652
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $563,423 | 12,332,063 |
kWh
|
$0.046 |
Electricity Demand | $196,085 | 18,795 |
kW-mo/yr
|
$10.43 |
Natural Gas | $5,700 | 705 |
MMBtu
|
$8.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $764,504 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,200 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $23,155 | $22,250 |
$17,254
375,147
kWh
|
$5,901
-
kW-mo/yr
|
- | - | |
02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $543,061 | $1,420,250 |
$491,520
10,688,160
kWh
|
$154,572
-
kW-mo/yr
|
$(-103,031.0)
-
MMBtu
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,455 | $6,625 |
$1,692
36,928
kWh
|
$1,763
-
kW-mo/yr
|
- | - | |
04 | 2.2515: Use optimum thickness insulation | $678 | $219 |
$516
11,137
kWh
|
$162
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,587 | $5,358 |
$2,629
57,151
kWh
|
$958
-
kW-mo/yr
|
- | - | |
06 | 2.7144: Install spectral reflectors / delamp | $4,788 | $5,180 |
$2,786
60,668
kWh
|
$2,002
-
kW-mo/yr
|
- | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,780 | $8,500 | - | - | - | $5,780 | |
08 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $180,000 | $27,000 | - | - |
$180,000
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $764,504 | $1,495,382 |
$516,397
11,229,191
kWh
|
$165,358
-
kW-mo/yr
|
$76,969
-
MMBtu
|
$5,780 | ||
TOTAL IMPLEMENTED | $33,200 | $36,327 |
$20,399
443,435
kWh
|
$7,021
-
kW-mo/yr
|
- | $5,780 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs