ITAC Assessment: SD0182
ITAC logo
ITAC Assessment: SD0182
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Manufacture architect and engineering pressure regulators
NAICS
n/a
SIC 3826: Laboratory Analytical Instruments
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 100,000
ft2
Annual Production 25,000
pieces
Production Hrs. Annual 4,674
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,365 1,258,206
kWh
Electricity Demand $38,123 4,524
kW-mo/yr
Natural Gas $10,621 1,866
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,623 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $3,749 $1,120 $2,737
35,463
kWh
$1,012
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,314 $8,154 $2,448
31,946
kWh
$866
-
kW-mo/yr
- -
03 2.7144: Install spectral reflectors / delamp $5,442 $6,980 $3,902
50,703
kWh
$1,540
-
kW-mo/yr
- -
04 3.4113: Treat and reuse rinse waters $1,680 $1,680 - - $1,680
-
gal
-
05 4.423: Move product using mechanical means $2,438 $924 - - - $2,438
TOTAL RECOMMENDED $16,623 $18,858 $9,087
118,112
kWh
$3,418
-
kW-mo/yr
$1,680
-
gal
$2,438
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs