ITAC Assessment: SD0181
ITAC logo
ITAC Assessment: SD0181
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Heat Transfer Products
NAICS
n/a
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 75,000
ft2
Annual Production 42,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,379 950,762
kWh
Electricity Demand $21,338 2,571
kW-mo/yr
Natural Gas $6,624 1,091
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $116,978 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,278

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,363 $2,363 $1,691
23,740
kWh
$672
-
kW-mo/yr
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,392 - $1,052
14,947
kWh
$340
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,773 $6,741 $1,366
19,343
kWh
$407
-
kW-mo/yr
- - -
04 2.7144: Install spectral reflectors / delamp $744 $1,190 $571
7,913
kWh
$173
-
kW-mo/yr
- - -
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $22,100 $9,000 - - - $22,100 -
06 3.8224: Convert to less toxic hydrocarbon cleaners $2,462 - - - $2,462
-
gal
- -
07 3.7134: Wash and reuse rags on-site $1,262 $1,600 - - - - $1,262
08 4.441: Install automatic packing equipment $25,182 $9,000 - - - $25,182 -
09 4.511: Expand operations into unused space $22,500 $49,750 - - - $22,500 -
10 4.321: Optimize production lot sizes and inventories $37,200 $24,000 - - - $37,200 -
TOTAL RECOMMENDED $116,978 $103,644 $4,680
65,943
kWh
$1,592
-
kW-mo/yr
$2,462
-
gal
$106,982 $1,262
TOTAL IMPLEMENTED $57,278 $29,894 $4,680
65,943
kWh
$1,592
-
kW-mo/yr
$2,462
-
gal
$47,282 $1,262
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs