ITAC Assessment: SD0180
ITAC logo
ITAC Assessment: SD0180
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Custom Molding
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 50,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $122,248 2,330,891
kWh
Electricity Demand $48,172 5,748
kW-mo/yr
Natural Gas $707 67
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $61,375 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $61,375

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $3,799 $2,450 $2,873
55,100
kWh
$926
-
kW-mo/yr
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $35,902 $125,100 $23,285
447,831
kWh
$12,617
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,297 $2,900 $1,021
19,637
kWh
$276
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,515 $3,456 $1,048
20,223
kWh
$467
-
kW-mo/yr
-
05 2.7144: Install spectral reflectors / delamp $3,072 $2,740 $2,183
41,911
kWh
$889
-
kW-mo/yr
-
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $8,500 $2,000 - - $8,500
07 4.321: Optimize production lot sizes and inventories $7,290 $21,000 - - $7,290
TOTAL RECOMMENDED $61,375 $159,646 $30,410
584,702
kWh
$15,175
-
kW-mo/yr
$15,790
TOTAL IMPLEMENTED $61,375 $159,646 $30,410
584,702
kWh
$15,175
-
kW-mo/yr
$15,790
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs