| Assessment Year | 1997 |
|---|---|
| Principal Product | Custom Molding |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
50,000
ft2
|
| Annual Production | 2,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $122,248 | 2,330,891 |
kWh
|
$0.052 |
| Electricity Demand | $48,172 | 5,748 |
kW-mo/yr
|
$8.38 |
| Natural Gas | $707 | 67 |
MMBtu
|
$10.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $61,375 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $61,375 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $3,799 | $2,450 |
$2,873
55,100
kWh
|
$926
-
kW-mo/yr
|
- | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $35,902 | $125,100 |
$23,285
447,831
kWh
|
$12,617
-
kW-mo/yr
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,297 | $2,900 |
$1,021
19,637
kWh
|
$276
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,515 | $3,456 |
$1,048
20,223
kWh
|
$467
-
kW-mo/yr
|
- | |
| 05 | 2.7144: Install spectral reflectors / delamp | $3,072 | $2,740 |
$2,183
41,911
kWh
|
$889
-
kW-mo/yr
|
- | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $8,500 | $2,000 | - | - | $8,500 | |
| 07 | 4.321: Optimize production lot sizes and inventories | $7,290 | $21,000 | - | - | $7,290 | |
| TOTAL RECOMMENDED | $61,375 | $159,646 |
$30,410
584,702
kWh
|
$15,175
-
kW-mo/yr
|
$15,790 | ||
| TOTAL IMPLEMENTED | $61,375 | $159,646 |
$30,410
584,702
kWh
|
$15,175
-
kW-mo/yr
|
$15,790 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs