Assessment Year | 1997 |
---|---|
Principal Product | Multi-layer printed circuit boards |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
82,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 7,803
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $410,023 | 5,746,190 |
kWh
|
$0.071 |
Electricity Demand | $107,968 | 14,246 |
kW-mo/yr
|
$7.58 |
Natural Gas | $60,447 | 26,769 |
MMBtu
|
$2.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $148,371 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $122,797 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $6,578 | $9,930 |
$5,027
70,926
kWh
|
$1,551
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.1224: Replace boiler | $19,420 | $83,000 | - | - |
$19,420
-
MMBtu
|
- | - | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $6,154 | $3,900 | - | - |
$6,154
-
MMBtu
|
- | - | - | |
04 | 2.2515: Use optimum thickness insulation | $3,056 | $2,170 | - | - |
$3,056
-
MMBtu
|
- | - | - | |
05 | 2.2515: Use optimum thickness insulation | $1,916 | $720 | - | - |
$1,916
-
MMBtu
|
- | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,318 | $6,500 |
$2,893
40,739
kWh
|
$1,425
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,228 | $13,068 |
$5,418
76,202
kWh
|
$810
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7144: Install spectral reflectors / delamp | $17,960 | $11,180 |
$15,559
219,226
kWh
|
$2,401
-
kW-mo/yr
|
- | - | - | - | |
09 | 3.6112: Use filter and drying oven to reduce sludge volume | $4,758 | $3,000 | - | - | - | - |
$4,758
-
lb
|
- | |
10 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $5,045 | - | - | - | - | - | - | $5,045 | |
11 | 3.4115: Recover and reuse cooling water | $3,300 | $2,000 | - | - | - |
$3,300
-
gal
|
- | - | |
12 | 4.444: Install system to collect scrap | $69,638 | $20,000 | - | - | - | - | - | $69,638 | |
TOTAL RECOMMENDED | $148,371 | $155,468 |
$28,897
407,093
kWh
|
$6,187
-
kW-mo/yr
|
$30,546
-
MMBtu
|
$3,300
-
gal
|
$4,758
-
lb
|
$74,683 | ||
TOTAL IMPLEMENTED | $122,797 | $68,568 |
$28,897
407,093
kWh
|
$6,187
-
kW-mo/yr
|
$4,972
-
MMBtu
|
$3,300
-
gal
|
$4,758
-
lb
|
$74,683 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs