| Assessment Year | 1996 |
|---|---|
| Principal Product | Automotive Batteries |
| NAICS |
n/a
|
| SIC | 3691: Storage Batteries |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
254,000
ft2
|
| Annual Production | 2,200,000
pieces
|
| Production Hrs. Annual | 6,125
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,604,769 | 26,303,928 |
kWh
|
$0.061 |
| Electricity Demand | $383,479 | 60,471 |
kW-mo/yr
|
$6.34 |
| Electricity Fees | $1,988,248 | - |
|
- |
| Natural Gas | $113,358 | 50,400 |
MMBtu
|
$2.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $52,544 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $52,544 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $5,249 | $3,880 |
$5,249
73,271
kWh
|
- | - | |
| 02 | 2.7145: Install skylights | $4,543 | $14,692 |
$4,543
41,325
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,155 | $8,557 |
$5,155
71,805
kWh
|
- | - | |
| 04 | 2.7144: Install spectral reflectors / delamp | $11,009 | $11,610 |
$11,009
150,059
kWh
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $3,443 | $665 |
$3,443
47,479
kWh
|
- | - | |
| 06 | 3.7211: Modify material application methods | $1,920 | $350 | - |
$1,920
-
gal
|
- | |
| 07 | 3.8143: Recycle cleaning solvent and reuse | $5,625 | $50 | - |
$5,625
-
gal
|
- | |
| 08 | 3.1191: Change procedures / equipment / operating conditions | $15,600 | - | - | - | $15,600 | |
| TOTAL RECOMMENDED | $52,544 | $39,804 |
$29,399
383,939
kWh
|
$7,545
-
gal
|
$15,600 | ||
| TOTAL IMPLEMENTED | $52,544 | $39,804 |
$29,399
383,939
kWh
|
$7,545
-
gal
|
$15,600 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs