Assessment Year | 1996 |
---|---|
Principal Product | Plated Metals and Plastic Products |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
163,651
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 3,960
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $725,987 | 11,097,304 |
kWh
|
$0.065 |
Electricity Demand | $211,349 | 30,274 |
kW-mo/yr
|
$6.98 |
Natural Gas | $247,501 | 72,012 |
MMBtu
|
$3.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $82,518 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $75,150 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $18,102 | $21,570 |
$18,102
199,590
kWh
|
- | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,242 | $3,920 |
$2,242
31,653
kWh
|
- | - | - | |
03 | 2.1242: Minimize boiler blowdown with better feedwater treatment | $10,042 | $4,160 | - |
$10,042
-
MMBtu
|
- | - | |
04 | 2.2136: Install / repair insulation on steam lines | $2,408 | $3,077 | - |
$2,408
-
MMBtu
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $7,368 | $5,825 |
$7,368
75,615
kWh
|
- | - | - | |
06 | 3.4151: Minimize water usage | $7,565 | $3,410 | - | - |
$7,565
-
Tgal
|
- | |
07 | 3.6114: Use precipitating agents in waste water treatment that produce the least quantity of waste | $34,791 | $5,000 | - | - | - |
$34,791
-
lb
|
|
TOTAL RECOMMENDED | $82,518 | $46,962 |
$27,712
306,858
kWh
|
$12,450
-
MMBtu
|
$7,565
-
Tgal
|
$34,791
-
lb
|
||
TOTAL IMPLEMENTED | $75,150 | $41,137 |
$20,344
231,243
kWh
|
$12,450
-
MMBtu
|
$7,565
-
Tgal
|
$34,791
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs