| Assessment Year | 1996 |
|---|---|
| Principal Product | Computer Ribbon Cartridges, Ink Pens |
| NAICS |
n/a
|
| SIC | 3951: Pens, Mechanical Pencils, and Parts |
| Sales Range | $50 M to 100M |
| # of Employees | 150 |
| Plant Area |
65,000
ft2
|
| Annual Production | 25,000,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $101,227 | 1,823,857 |
kWh
|
$0.056 |
| Electricity Demand | $90,245 | 5,253 |
kW-mo/yr
|
$17.18 |
| Natural Gas | $1,381 | 144 |
MMBtu
|
$9.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $44,295 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $44,295 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $2,761 | $1,740 |
$2,761
34,291
kWh
|
- | |
| 02 | 2.6218: Turn off equipment when not in use | $4,893 | - |
$4,893
60,668
kWh
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,292 | $1,960 |
$1,292
22,274
kWh
|
- | |
| 04 | 2.7145: Install skylights | $4,665 | $7,316 |
$4,665
42,204
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,291 | $9,923 |
$5,291
42,204
kWh
|
- | |
| 06 | 2.7144: Install spectral reflectors / delamp | $19,575 | $20,980 |
$19,575
207,210
kWh
|
- | |
| 07 | 2.7135: Install occupancy sensors | $2,038 | $1,387 |
$2,038
16,120
kWh
|
- | |
| 08 | 3.6192: Use a less expensive method of waste removal | $3,780 | - | - |
$3,780
-
lb
|
|
| TOTAL RECOMMENDED | $44,295 | $43,306 |
$40,515
424,971
kWh
|
$3,780
-
lb
|
||
| TOTAL IMPLEMENTED | $44,295 | $43,306 |
$40,515
424,971
kWh
|
$3,780
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs