| Assessment Year | 1996 |
|---|---|
| Principal Product | Livestock Feeds |
| NAICS |
n/a
|
| SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
18,500
ft2
|
| Annual Production | 214,200
ton
|
| Production Hrs. Annual | 8,007
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $179,855 | 3,033,412 |
kWh
|
$0.059 |
| Electricity Demand | $60,151 | 9,281 |
kW-mo/yr
|
$6.48 |
| Natural Gas | $130,021 | 50,292 |
MMBtu
|
$2.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $41,282 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $41,282 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $7,877 | $15,010 |
$7,877
97,890
kWh
|
- | - | |
| 02 | 2.7261: Install timers and/or thermostats | $2,749 | $1,875 |
$2,749
22,274
kWh
|
- | - | |
| 03 | 2.2515: Use optimum thickness insulation | $2,174 | $1,578 | - |
$2,174
-
MMBtu
|
- | |
| 04 | 2.2136: Install / repair insulation on steam lines | $762 | $750 | - |
$762
-
MMBtu
|
- | |
| 05 | 3.5217: Reuse / recycle/ sell paper products | $15,120 | $3,000 | - | - |
$15,120
-
lb
|
|
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $12,600 | $11,000 | - | - |
$12,600
-
lb
|
|
| TOTAL RECOMMENDED | $41,282 | $33,213 |
$10,626
120,164
kWh
|
$2,936
-
MMBtu
|
$27,720
-
lb
|
||
| TOTAL IMPLEMENTED | $41,282 | $33,213 |
$10,626
120,164
kWh
|
$2,936
-
MMBtu
|
$27,720
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs