| Assessment Year | 1996 |
|---|---|
| Principal Product | Polyethylene and Textile Bags |
| NAICS |
n/a
|
| SIC | 2393: Textile Bags |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
375,000
ft2
|
| Annual Production | 44,000,000
lb
|
| Production Hrs. Annual | 8,125
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $211,483 | 3,695,487 |
kWh
|
$0.057 |
| Electricity Demand | $184,583 | 10,898 |
kW-mo/yr
|
$16.94 |
| Electricity Fees | $396,066 | - |
|
- |
| Natural Gas | $23,279 | 3,151 |
MMBtu
|
$7.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $106,032 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $11,552 | $14,760 |
$11,552
133,060
kWh
|
- | - | - | |
| 02 | 2.3137: Use power during off-peak periods | $37,136 | - |
$37,136
85,580
kWh
|
- | - | - | |
| 03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $1,627 | $1,495 |
$1,627
20,809
kWh
|
- | - | - | |
| 04 | 2.2511: Insulate bare equipment | $1,130 | $284 |
$1,130
21,688
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,848 | $13,338 |
$10,848
91,735
kWh
|
- | - | - | |
| 06 | 2.7144: Install spectral reflectors / delamp | $18,160 | $15,165 |
$18,160
158,558
kWh
|
- | - | - | |
| 07 | 2.7135: Install occupancy sensors | $2,449 | $1,600 |
$2,449
18,464
kWh
|
- | - | - | |
| 08 | 3.8141: Regenerate cleaning solvent on-site and reuse | $18,430 | $7,200 | - |
$18,430
-
gal
|
- | - | |
| 09 | 3.5311: Recover and reuse waste material | $3,500 | - | - | - |
$3,500
-
lb
|
- | |
| 10 | 3.5311: Recover and reuse waste material | $1,200 | $500 | - | - | - | $1,200 | |
| TOTAL RECOMMENDED | $106,032 | $54,342 |
$82,902
529,894
kWh
|
$18,430
-
gal
|
$3,500
-
lb
|
$1,200 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs