Assessment Year | 1996 |
---|---|
Principal Product | Jewelry |
NAICS |
n/a
|
SIC | 3915: Jewelers' Findings and Materials, and Lapidary Work |
Sales Range | $50 M to 100M |
# of Employees | 330 |
Plant Area |
70,000
ft2
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 3,536
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,188 | 1,287,222 |
kWh
|
$0.055 |
Electricity Demand | $81,729 | 4,622 |
kW-mo/yr
|
$17.68 |
Natural Gas | $12,025 | 1,664 |
MMBtu
|
$7.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,256 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,721 | $1,920 |
$1,721
14,947
kWh
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $2,606 | - |
$2,606
11,430
kWh
|
- | - | |
03 | 2.2511: Insulate bare equipment | $1,486 | $424 |
$1,486
28,136
kWh
|
- | - | |
04 | 2.7144: Install spectral reflectors / delamp | $11,034 | $17,125 |
$11,034
97,597
kWh
|
- | - | |
05 | 2.7135: Install occupancy sensors | $1,465 | $574 |
$1,465
12,896
kWh
|
- | - | |
06 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $895 | $190 |
$895
7,913
kWh
|
- | - | |
07 | 3.4113: Treat and reuse rinse waters | $2,069 | $1,300 | - |
$2,069
-
Tgal
|
- | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,980 | $600 | - | - |
$1,980
-
lb
|
|
TOTAL RECOMMENDED | $23,256 | $22,133 |
$19,207
172,919
kWh
|
$2,069
-
Tgal
|
$1,980
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs