| Assessment Year | 1996 |
|---|---|
| Principal Product | Jewelry |
| NAICS |
n/a
|
| SIC | 3915: Jewelers' Findings and Materials, and Lapidary Work |
| Sales Range | $50 M to 100M |
| # of Employees | 330 |
| Plant Area |
70,000
ft2
|
| Annual Production | 4,000,000
lb
|
| Production Hrs. Annual | 3,536
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $70,188 | 1,287,222 |
kWh
|
$0.055 |
| Electricity Demand | $81,729 | 4,622 |
kW-mo/yr
|
$17.68 |
| Natural Gas | $12,025 | 1,664 |
MMBtu
|
$7.23 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,256 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,721 | $1,920 |
$1,721
14,947
kWh
|
- | - | |
| 02 | 2.6218: Turn off equipment when not in use | $2,606 | - |
$2,606
11,430
kWh
|
- | - | |
| 03 | 2.2511: Insulate bare equipment | $1,486 | $424 |
$1,486
28,136
kWh
|
- | - | |
| 04 | 2.7144: Install spectral reflectors / delamp | $11,034 | $17,125 |
$11,034
97,597
kWh
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $1,465 | $574 |
$1,465
12,896
kWh
|
- | - | |
| 06 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $895 | $190 |
$895
7,913
kWh
|
- | - | |
| 07 | 3.4113: Treat and reuse rinse waters | $2,069 | $1,300 | - |
$2,069
-
Tgal
|
- | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,980 | $600 | - | - |
$1,980
-
lb
|
|
| TOTAL RECOMMENDED | $23,256 | $22,133 |
$19,207
172,919
kWh
|
$2,069
-
Tgal
|
$1,980
-
lb
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs