Assessment Year | 1996 |
---|---|
Principal Product | Aluminum Die Castings |
NAICS |
n/a
|
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
58,000
ft2
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 4,284
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $181,560 | 2,681,125 |
kWh
|
$0.068 |
Electricity Demand | $53,573 | 17,371 |
kW-mo/yr
|
$3.08 |
Natural Gas | $128,916 | 39,598 |
MMBtu
|
$3.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,790 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $9,127 | $12,660 |
$9,127
103,458
kWh
|
- | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $16,412 | $46,000 | - |
$16,412
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,410 | $450 |
$2,410
28,136
kWh
|
- | - | |
04 | 2.2611: Moderate cooling tower outlet temperature | $318 | $200 |
$318
4,982
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,467 | $2,141 |
$2,467
28,722
kWh
|
- | - | |
06 | 2.7144: Install spectral reflectors / delamp | $6,700 | $4,730 |
$6,700
78,253
kWh
|
- | - | |
07 | 2.7135: Install occupancy sensors | $673 | $517 |
$673
7,913
kWh
|
- | - | |
08 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,683 | $450 | - | - |
$1,683
-
Tgal
|
|
TOTAL RECOMMENDED | $39,790 | $67,148 |
$21,695
251,464
kWh
|
$16,412
-
MMBtu
|
$1,683
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs