Assessment Year | 1995 |
---|---|
Principal Product | Spas |
NAICS |
n/a
|
SIC | 3088: Plastics Plumbing Fixtures |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
90,000
ft2
|
Annual Production | 15,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $248,299 | 2,724,795 |
kWh
|
$0.091 |
Natural Gas | $794 | 86 |
MMBtu
|
$9.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,469 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $49,469 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,630 | $2,690 |
$1,630
17,878
kWh
|
- | - | |
02 | 2.2511: Insulate bare equipment | $4,498 | $630 |
$4,498
49,238
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,318 | $20 |
$2,318
25,498
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,895 | $400 |
$1,895
20,809
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,676 | $10,950 |
$14,676
160,903
kWh
|
- | - | |
06 | 2.7144: Install spectral reflectors / delamp | $5,389 | $6,575 |
$5,389
54,513
kWh
|
- | - | |
07 | 2.7135: Install occupancy sensors | $2,552 | $1,559 |
$2,552
25,791
kWh
|
- | - | |
08 | 2.7134: Use photocell controls | $1,578 | $560 |
$1,578
15,240
kWh
|
- | - | |
09 | 3.8143: Recycle cleaning solvent and reuse | $14,753 | $10,000 | - |
$14,753
-
Tgal
|
- | |
10 | 3.1175: Use a different or recycled raw material | $180 | - | - | - |
$180
-
lb
|
|
TOTAL RECOMMENDED | $49,469 | $33,384 |
$34,536
369,870
kWh
|
$14,753
-
Tgal
|
$180
-
lb
|
||
TOTAL IMPLEMENTED | $49,469 | $33,384 |
$34,536
369,870
kWh
|
$14,753
-
Tgal
|
$180
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs