ITAC Assessment: SD0117
ITAC logo
ITAC Assessment: SD0117
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Spas
NAICS
n/a
SIC 3088: Plastics Plumbing Fixtures
Sales Range $50
M
to 100
M
# of Employees 500
Plant Area 90,000
ft2
Annual Production 15,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $248,299 2,724,795
kWh
Natural Gas $794 86
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,469 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $49,469

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Water Disposal Savings Solid Waste (non-haz) Savings
01 2.4133: Use most efficient type of electric motors $1,630 $2,690 $1,630
17,878
kWh
- -
02 2.2511: Insulate bare equipment $4,498 $630 $4,498
49,238
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,318 $20 $2,318
25,498
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,895 $400 $1,895
20,809
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $14,676 $10,950 $14,676
160,903
kWh
- -
06 2.7144: Install spectral reflectors / delamp $5,389 $6,575 $5,389
54,513
kWh
- -
07 2.7135: Install occupancy sensors $2,552 $1,559 $2,552
25,791
kWh
- -
08 2.7134: Use photocell controls $1,578 $560 $1,578
15,240
kWh
- -
09 3.8143: Recycle cleaning solvent and reuse $14,753 $10,000 - $14,753
-
Tgal
-
10 3.1175: Use a different or recycled raw material $180 - - - $180
-
lb
TOTAL RECOMMENDED $49,469 $33,384 $34,536
369,870
kWh
$14,753
-
Tgal
$180
-
lb
TOTAL IMPLEMENTED $49,469 $33,384 $34,536
369,870
kWh
$14,753
-
Tgal
$180
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Water Disposal Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs