| Assessment Year | 1995 |
|---|---|
| Principal Product | Concrete Blocks |
| NAICS |
n/a
|
| SIC | 3271: Concrete Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 185 |
| Plant Area |
479,160
ft2
|
| Annual Production | 9,000,000
pieces
|
| Production Hrs. Annual | 3,770
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $110,105 | 888,335 |
kWh
|
$0.12 |
| Natural Gas | $1,623 | 214 |
MMBtu
|
$7.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,699 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,429 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $7,427 | $6,900 |
$7,427
59,789
kWh
|
|
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,270 | $1,750 |
$1,270
10,258
kWh
|
|
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $633 | - |
$633
4,982
kWh
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,025 | $2,700 |
$1,025
8,206
kWh
|
|
| 05 | 2.7144: Install spectral reflectors / delamp | $1,352 | $825 |
$1,352
10,551
kWh
|
|
| 06 | 2.7135: Install occupancy sensors | $251 | $320 |
$251
2,052
kWh
|
|
| 07 | 2.7134: Use photocell controls | $1,351 | $336 |
$1,351
10,258
kWh
|
|
| 08 | 2.7132: Install timers on light switches in little used areas | $390 | $175 |
$390
2,931
kWh
|
|
| TOTAL RECOMMENDED | $13,699 | $13,006 |
$13,699
109,027
kWh
|
||
| TOTAL IMPLEMENTED | $12,429 | $11,256 |
$12,429
98,769
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs