ITAC Assessment: SD0016
ITAC logo
ITAC Assessment: SD0016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product TRANSPORTATION EQUIPMENT
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 82
Plant Area
n/a
Annual Production 550
pieces
Production Hrs. Annual 4,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $143,105 1,555,686
kWh
Natural Gas $10,384 1,623
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,749 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $564 $423 $564
6,155
kWh
- -
02 2.6218: Turn off equipment when not in use $5,920 $505 $(-224.0)
(-2,345)
kWh
$6,144
-
MMBtu
-
03 2.4322: Use or replace with energy efficient substitutes $3,341 $3,300 - $3,341
-
MMBtu
-
04 2.2531: Re-size charging openings or add movable cover or door $459 $109 $459
4,982
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,115 $448 $883
9,672
kWh
- $232
06 2.7111: Reduce illumination to minimum necessary levels $12,350 $30,068 $11,145
123,681
kWh
- $1,205
TOTAL RECOMMENDED $23,749 $34,853 $12,827
142,145
kWh
$9,485
-
MMBtu
$1,437
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs