ITAC Assessment: SD0008
ITAC logo
ITAC Assessment: SD0008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product TUBE BENDING MACHINES
NAICS
n/a
SIC 3542: Machine Tools, Metal Forming Types
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area
n/a
Annual Production 100
pieces
Production Hrs. Annual 4,080
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $90,398 1,077,374
kWh
Natural Gas $774 109
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,640 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,640

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $170 $190 $170
2,052
kWh
- -
02 2.2437: Recover waste heat from equipment $513 $600 - $513
-
MMBtu
-
03 2.6212: Turn off equipment during breaks, reduce operating time $492 $120 $492
5,862
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,281 $3,150 $573
6,741
kWh
- $1,708
05 2.7123: Keep lamps and reflectors clean $1,113 $2,940 $1,006
12,016
kWh
- $107
06 2.7123: Keep lamps and reflectors clean $4,128 $13,356 $3,792
45,135
kWh
- $336
07 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $4,016 $9,150 $3,645
51,290
kWh
- $371
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,430 $2,080 $887
10,551
kWh
- $543
09 2.7226: Use computer programs to optimize hvac performance $3,497 $9,900 $3,497
41,618
kWh
- -
TOTAL RECOMMENDED $17,640 $41,486 $14,062
175,265
kWh
$513
-
MMBtu
$3,065
TOTAL IMPLEMENTED $17,640 $41,486 $14,062
175,265
kWh
$513
-
MMBtu
$3,065
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs