ITAC Assessment: OR0834
ITAC logo
ITAC Assessment: OR0834
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Greenhouse Space
NAICS 001114: Greenhouse, Nursery, and Floriculture Production
SIC 0182: Food Crops Grown Under Cover
Sales Range less than $500
k
# of Employees 12
Plant Area 108,000
ft2
Annual Production 21
units
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $110,348 715,477
kWh
Natural Gas $3,730 281
MMBtu
Other Energy $80,592 4,052
MMBtu
Waste Disposal Costs
Water Usage $7,058 2,064
Tgal
Water Disposal $4,878 1
Tgal
Solid Waste (non-haz) $8,619 1
lb
TOTAL YEARLY COSTS $215,225
RECOMMENDED SAVINGS* $32,590 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Energy Savings Solid Waste (non-haz) Savings
01 2.8114: Change rate schedules or other changes in utility service $1,775 - - - - $1,775
-
lb
02 2.7142: Utilize higher efficiency lamps and/or ballasts $990 $1,429 $697
12,444
kWh
$293
-
kW-mo/yr
- -
03 2.2136: Install / repair insulation on steam lines $4,602 $492 - - $4,602
-
MMBtu
-
04 2.9114: Use solar heat to make electricty $16,359 $365,845 $12,386
229,219
kWh
$3,973
-
kW-mo/yr
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $814 $20,990 $257
4,594
kWh
$557
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $8,050 $279,941 $8,050
143,757
kWh
- - -
TOTAL RECOMMENDED $32,590 $668,697 $21,390
390,014
kWh
$4,823
-
kW-mo/yr
$4,602
-
MMBtu
$1,775
-
lb
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Energy Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs