ITAC Assessment: OR0829
ITAC logo
ITAC Assessment: OR0829
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $5
M
to 10
M
# of Employees 8
Plant Area 520,000
ft2
Annual Production 2,365,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $258,745 3,282,960
kWh
Electricity Demand $104,359 10,309
kW-mo/yr
Electricity Fees $14,170 -
Natural Gas $29,484 4,140
MMBtu
TOTAL YEARLY COSTS $406,758
RECOMMENDED SAVINGS* $66,484 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $510 - $441
4,950
kWh
$69
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,055 $1,887 $2,585
29,039
kWh
$470
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,322 $8,827 $1,322
14,489
kWh
- -
04 2.9114: Use solar heat to make electricty $49,956 $132,300 $49,180
83,589
kWh
$776
-
kW-mo/yr
-
05 2.7232: Replace existing hvac unit with high efficiency model $11,641 $100,000 - - $11,641
-
MMBtu
TOTAL RECOMMENDED $66,484 $243,014 $53,528
132,067
kWh
$1,315
-
kW-mo/yr
$11,641
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs