| Assessment Year | 2026 |
|---|---|
| Principal Product | Wood Veneer |
| NAICS | 321212: Softwood Veneer and Plywood Manufacturing |
| SIC | 2436: Softwood Veneer and Plywood |
| Sales Range | $50 M to 100M |
| # of Employees | 71 |
| Plant Area |
130,000
ft2
|
| Annual Production | 321,338
units
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $761,036 | 11,040,000 |
kWh
|
$0.069 |
| Electricity Demand | $398,910 | 28,933 |
kW-mo/yr
|
$13.79 |
| Electricity Fees | $63,720 | - |
|
- |
| Natural Gas | $563,186 | 106,665 |
MMBtu
|
$5.28 |
| TOTAL YEARLY COSTS | $1,786,852 | |||
| RECOMMENDED SAVINGS* | $2,843,684 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,835 | - |
$4,618
66,995
kWh
|
$2,217
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,685 | - |
$1,678
24,342
kWh
|
$1,007
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4323: Use optimum size and capacity equipment | $2,712,540 | $32,000 | - | - | - | - | $78,384 | $2,634,156 | |
| 04 | 2.2437: Recover waste heat from equipment | $78,209 | $1,612 |
$2,043
29,635
kWh
|
- | - |
$7,206
-
MMBtu
|
- | $68,960 | |
| 05 | 2.2514: Cover open tanks | $1,065 | $184 | - | - | - |
$1,065
-
MMBtu
|
- | - | |
| 06 | 2.3212: Optimize plant power factor | $7,574 | $55,435 | - | - | $7,574 | - | - | - | |
| 07 | 2.9114: Use solar heat to make electricty | $34,776 | $600,754 |
$34,776
504,518
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $2,843,684 | $689,985 |
$43,115
625,490
kWh
|
$3,224
-
kW-mo/yr
|
$7,574 |
$8,271
-
MMBtu
|
$78,384 | $2,703,116 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs